Zum Inhalt wechseln

The Dragon's Head Blog: Construction Update on International Center in Dunedin, Florida for March 21, 2016

Restoration work continues at our second International Center.  Framing teams continue construction of the load-bearing walls and have begun replacement of the girders on the second floor of the northeast wing.

NEWingSecondFloorFraming3-21

Plumbers continue to work in the southeast wing.

Plumbers2_3-17 Plumbers1_3-16

The lobby scaffolding around the new support column has been removed.

MainLobbyColumnNoScaffeling3-15

Work on the new lobby doors facing the courtyard has started. Stucco was removed and vertical and horizontal support beams are being installed. Scaffolding will be put up to support the east wall during the preparations for the new doors.

ScaffolingLobbyWallOutsidePrep3-21

Installation of the new windows is progressing apace with the southeast wing second floor almost completed.

Windows3-18

 

Schreibe einen Kommentar

Deine E-Mail-Adresse wird nicht veröffentlicht. Erforderliche Felder sind mit * markiert

Cookie Control Icon