Construction inside of Building A and surrounding property is increasing….

Trees that had been scheduled for removal in the new parking lot are being removed to make room for more heavy equipment.

Workers are continuing to rebuild the first floor and new elevator shaft that is taking the place of the old stairwell. New test hurricane windows are being installed to make sure no issues arise during installation and the appearance is the same as the originals. Electricians are now in the building running lights on all three floors and electrical boxes where needed. Masons have completed stem walls to support the dining room and patio areas.

 