The Dragon's Head Blog: International Center Florida Construction Update January 26, 2016

International Center Florida Construction Update for the week ending January 21, 2016

Building A
Interior Framing and strapping continues throughout the first floor SE wing.

1stFloorInteriorStrappingSEwing FramingContinues1stFloor
Replacement of damaged floor joists continues on second floor NE wing.
Second FloorJoistRepairsTempWallSecondFloor
The elevator and restrooms support walls were constructed and cells filled with concrete. These walls will support floor joists in the restrooms and the elevator.
     Elevator support walls cells filledRestroomsupportwallCellsFilledIMG_3616
The Main Lobby Support scaffolding is awaiting approval from the structional engineer before repairs can begin.
LobbyScaffolding
Masons also poured cells in the ADA lift on the front porch. The front porch patio is being readied for reconstruction.
  IMG_3625FrontPorchSupportWallRebarb
New window installation is ongoing.
 EastCenterWindowsInstalled   NewWindowsThirdandSecond
Check back often for more updates!!!