The Dragon's Head Blog: International Center Florida Construction Update for the Week Ending July 17, 2016
Another exciting week has taken place at the International Center Florida. The stair tower on the northwest side of the building has a roof. Next will be the tile.
Drywall is now completed on the second floor of the southeast, northwest and northeast corridor walls.
The window installers are busy in the northeast wing.
The new electrical room and data/communication room within have been framed.
Plumbing is being installed in the northeast, southeast and northwest wings.
New lobby stairs are being installed.
Check back soon to learn about more advances on this home for practicing Taoist Tai Chi™ arts.